Chandler City Council
members grilled Salt River Project
officials Wednesday evening about a host
of issues related to the installation of
a new Kyrene Corridor power line.
The meeting of the council’s Municipal
Utilities and Public Works Committee
provided a chance for council members to
discuss with SRP officials the various
options for preventing service
interruptions, which SRP insists will be
inevitable by summer 2007 without the
construction of a new 69 kV power line
to run between two substations.
While Wednesday’s meeting was public as
required by Arizona’s open-meeting
statute, city staff, SRP employees and
reporters far outnumbered residents, a
stark contrast to two previous,
emotionally charged public meetings on
the issue which swarmed with frustrated
residents.
Two members of the public did speak
briefly, thanking the council and SRP
for holding the meeting and pleading
with SRP to “find it in your hearts” to
eat the cost of burying the lines.
SRP, however, refuses to take such
action, worrying about the precedent for
future projects and saying all of the
utility’s costs are ultimately spread
between all of its customers across the
Valley.
It wouldn’t be fair, SRP says, to burden
the entire Valley with the costs of
burying the lines in just a few
neighborhoods.
Chandler Mayor Boyd Dunn directed the
city staff to compile information about
the city’s aesthetic fund, a grant from
SRP given yearly as a percentage of the
total amount being spent by the utility
in the city for them “to use at their
discretion,” said SRP Spokesman Scott
Harelson.
For this year, Chandler was allocated
$1.1 million for the fund, according to
a city official. That money is usually
spent to underground much smaller 12 kV
lines as well as landscape projects and
walls to enclose substations.
The funds are not typically spent to
underground 69 kV lines, and would fall
far short of covering the expensive
Hanger-Houston project in question.
Even if allocated in its entirety to the
Hanger-Houston project, the $1.1 million
fund would cover burial for less than
half a mile.
Tempe officials could not immediately be
reached for information about the amount
of aesthetic funds it receives from SRP.
Because Tempe is landlocked with very
little undeveloped land, power expansion
in the city is rare, the amount it
receives is likely considerable smaller
than Chandler’s fund.
Why it is
needed
SRP’s manager for transmission planning,
Rob Kondziolka, said the expansion is
necessary because there will simply be
too much demand on the system, likening
the situation to stringing too many
strands of Christmas lights together.
In the power line case, the lines heat
up and begin to sag, increasing the risk
of failure. The added line, which would
run from the Hanger substation near
Guadalupe and Price Roads to the Houston
substation near McClintock Drive and Ray
Road, would add an extra redundancy to
prevent that from happening.
SRP said its engineers have studied all
possible alternatives, but none of them
does more than buy time, ultimately
requiring the Hanger-Houston connection
in the end.
All six of SRP’s proposed route options
require the construction of new poles in
some areas, which has angered nearby
residents concerned the lines will be
aesthetically displeasing and will lower
property values.
Residents and elected officials,
including the mayors of Chandler and
Tempe, have requested that the lines be
buried. SRP says burial is technically
feasible, but refuses to undertake the
project unless it is bankrolled by
someone else, citing the cost
differential—$3 million per mile to bury
the lines vs. $300,000 per mile to hang
them. In the past, SRP said at the
meeting, housing developers and
municipalities have been the entities to
fund line burials.
Burial is so expensive, explained Jogi
Gadok, SRP’s chief engineer assigned to
this project, because of trenching and
material costs. Powerful 69 kV lines
require deep and wide trenches. The
wire, which uses several-inch-thick
copper as the conductor, has risen in
price immensely in the past few years
due to skyrocketing copper prices. Today
it costs $50 to $60 per foot, as opposed
to a mere $1.25 per foot for overhead
wire.
That cost differential works out to
about $264,000 per mile for wire alone
when buried, as opposed to $6,600 per
mile for wire when suspended.
The time and labor required for line
burial would also prevent the line from
being energized by the time it is needed
in summer 2007. SRP says it is committed
to exploring options to buy time if
Tempe or Chandler decides to foot the
bill for all or part of the burial.
If the line is ultimately built above
ground, many residents favor a proposed
route that constructs the line south
from Guadalupe to Ray along Loop 101 and
west from there to McClintock.
Taking care not to rule out the route,
SRP’s manager of design and
construction, Joe Nowaczyk, said the
plan presents several technical hurdles
and would cost about 50 percent more
than the alternative routes, which run
along McClintock Drive.
The Arizona Department of
Transportation, which owns the land
surrounding Loop 101, by policy refuses
to grant permanent land rights for
utility poles around its freeways.
While ADOT is willing to work with SRP
on the project, Nowaczyk said, SRP is
concerned about investing in an
infrastructure with non-permanent access
to the land on which that infrastructure
sits.
“But that isn’t to say we wouldn’t look
at what they were willing to give us for
the project,” he said.
He added that any line
ultimately built along Loop 101 would
likely go up to the west of the Price
frontage road. |